Rio and the Mongolian government have spent most of 2018 negotiating multiple aspects of their pact to jointly develop Oyu Tolgoi, which is currently being expanded into a giant underground mine at at cost of $US5.3 billion.
Mongolia
has this year accused Rio subsidiaries of having outstanding tax bills
worth $US155 million, forced the mine to source electricity from
Mongolia's under-developed energy sector rather than continuing to
import power from China, and commenced a corruption investigation into
the 2009 agreement that govern's Rio's investment in the project and the
division of profits from it.
The two parties agreed to explore "cost reductions" on the giant project earlier this year, and a working party established by the Mongolian government is expected to report its findings before the end of October.Mongolian press reported in recent days that several of those matters were close to resolution, with reports quoting Mongolian parliamentarian Gombojavyn Zandanshatar as saying that interest rates on shareholder loans would be reduced.
The Mongolian
government owns 34 per cent of the mine, but does not have the funds to
cover its share of construction costs, and so has relied on loans from
Rio where interest rates can be up to 6.5 per cent above the London
interbank rate (LIBOR).
The reports also suggested that a new power station would be built at Mongolia's Tavaan Tolgoi coal deposit.
The reports also suggested that a new power station would be built at Mongolia's Tavaan Tolgoi coal deposit.
Rio
and its subsidiaries' preferred option had been to build a new power
station at the Oyu Tolgoi mine site in the belief it could be built
quicker, and within the four-year deadline Mongolia has set for
domestically sourced power.
Rio was unable to confirm the
suggestions in recent days, and it is believed that if finalised, they
would be material and therefore required to be disclosed to the Toronto
Stock Exchange by the Rio subsidiary that owns 66 per cent of the mine;
Turquoise Hill Resources.
Rio and its
subsidiaries may yet be forced into international arbitration with the
Mongolian government in a bid to resolve the disputes.
First production from the Oyu Tolgoi expansion could come as early as 2021, but Rio subsidiaries have suggested that "sustainable production" will occur from 2022 onward.
Source:https://www.afr.com
First production from the Oyu Tolgoi expansion could come as early as 2021, but Rio subsidiaries have suggested that "sustainable production" will occur from 2022 onward.
Rio
will on Tuesday report production data for the three months to
September 30, with coal miner Whitehaven scheduled to report production
data on the same day.
BHP and copper miner OZ Minerals will both publish quarterly production reports on Wednesday.Source:https://www.afr.com