Delays to coal production at Ovoot project in Mongolia

Energy Global reported that Australian mining firm Aspire Mining has delayed the start up of coal production from its Ovoot project in Mongolia.

The company announced that it has developed a cost saving strategy that will help maximize profits and minimize costs at the metallurgical coal mine.

The new plan hinges on the extension of the existing Trans Mongolian railway being completed in one phase. The extension, known as the Northern Rail Line will be built by Aspire’s wholly owned subsidiary, Northern Railways and is expected to be commiussioned in 2017.

At this point in time, Northern Railways remains in discussions with the Mongolian Government regarding permits. The company hopes to extend the existing rail line which spans approximately 406 kilometers from Erdenet to Moron by a further 222 kilometers that would connect the Ovoot coal project with Erdenet.

Last month, test results confirmed coal from the Ovoot project could be blended with non metallurgical coals from the state owned project at Tavan Tolgoi to produce good quality metallurgical coal.

Aspire have marked the Sainshand Industrial Park as an ideal site for blending this coal. The industrial park could be accessed via the Erdenet Ovoot rail line.

In a press release, Aspire said that construction of the rail extension would alleviate the need to built a sealed coal haul road and reduce capital expenditure by USD 98 million.

The company provided an estimated time line of progression with the rail line;
1. December 2013: Receive grant of rail concession from Mongolian Government for Erdenet Ovoot railway.
2. March 2014: Complete feasibility study for Erdenet Ovoot railway.
3. June 2014: Complete funding for development of railway and commence railway earthworks and construction.
4. 2017: Commissioning of both railway and Ovoot mine.

The company estimate development of the Ovoot project will take approximately 12 months and aim to time the commissioning of the mine with the commissioning of the rail project.

Cost saving strategy;
The rescheduled estimated start of coal production from the Ovoot project represents a fundamental shift in Aspire’s development strategy. The company has identified the lowest capital intensive start up costs, by using contractors wherever possible.

Aspire initially estimated the capital necessary for the Ovoot project would be USD 459 million, plus USD 265 million for the mining fleet. Sweeping changes to the projected costs mean that the revised figure for total mine capital expenditure is now USD 144 million.

Source - Energyglobal.com
Share:

0 comments:

Post a Comment

Facebook page

Powered by Blogger.

Categories

Advertising in Mongolia An Asian Development Bank Culture Editorial of the Mongolianviews education Environmental protection Famous Mongolians Foreigners in Mongolia Inner Mongolia Ivanhoe Mines Mongolia Adventure Mongolia agriculture Mongolia air pollution Mongolia analysis Mongolia and Armenia Mongolia and Asian Development Bank Mongolia and Australia Mongolia and Azerbaijan Mongolia and Belorussia Mongolia and Bulgaria Mongolia and Cambodia Mongolia and Canada Mongolia and central Asia Mongolia and China Mongolia and Cuba Mongolia and Czech Mongolia and donors Mongolia and EU Mongolia and Germany Mongolia and Hongkong Mongolia and Hungary Mongolia and IFC Mongolia and IMF Mongolia and Ind Mongolia and India Mongolia and Indonesia Mongolia and Inner Mongolia Mongolia and Iran Mongolia and Israel Mongolia and Italy Mongolia and Japan Mongolia and Kazakhstan Mongolia and Korea Mongolia and Kuwait Mongolia and Kyrgyzstan Mongolia and Malaysia Mongolia and Nato Mongolia and North Korean Mongolia and Poland Mongolia and Qatar Mongolia and Russia Mongolia and Russia and Mongolia and China Mongolia and Singapore Mongolia and South Korea Mongolia and Taiwan Mongolia and Thailand Mongolia and the world Mongolia and Tibet Mongolia and Turkey Mongolia and UK Mongolia and Ukraine Mongolia and UN Mongolia and US Mongolia and USA Mongolia and Vietnam Mongolia Banking Mongolia blind Mongolia Cashmere Mongolia Christianity Mongolia civic society Mongolia Corruption Mongolia crime Mongolia diplomacy Mongolia Economy Mongolia Education Mongolia Energy Mongolia environment Mongolia Finance Mongolia Health Mongolia History Mongolia holiday Mongolia in international media Mongolia Industries Mongolia investment Mongolia Joke Mongolia law Mongolia LGBT Mongolia medical Mongolia military Mongolia Mining Mongolia Mining Developments Mongolia Mortgage Mongolia natural disaster Mongolia news media Mongolia Nuclear Mongolia Petroleum Mongolia Politics Mongolia Poverty Mongolia public announcements Mongolia railways Mongolia Religion Mongolia slums Mongolia society Mongolia Sports Mongolia Stamp Mongolia Sumo Mongolia telecommunication Mongolia tourism Mongolia trade Mongolia Transportation Mongolia Urbanization Mongolia Wild Life Mongolian Agriculture Mongolian and Cuba Mongolian Archeology Mongolian Climate Mongolian Food Mongolian Gay Mongolian Government news Mongolian History Mongolian Kazakh Mongolian Meat Mongolian Military Mongolian Mining Development Mongolian Movie Mongolian News Mongolian Parliament Mongolian Political news Mongolian Press Mongolian Songs Mongolian Sumo Mongolian Women Mongolian Youth Mongolians abroad Moninfo Opinion Oyu Tolgoi Investment Agreement Photo news Press Release Rio Tinto Tavan Tolgoi coal mine Ulaanbaatar development Weird expatriates in Mongolia World bank and Mongolia

Blog Archive

Followers